UUSM - About Us - Building News
Building and Capital Campaign
February, 2008
Revised Building Project Plan
On Sunday, February 10, at 12:30 p.m., there will be a Special Business Meeting of Church Members
to discuss and vote on the following:
Agenda Item #1:
To authorize the Board of Directors to proceed with detailed
construction design and obtain city approval for a revised plan
for construction and remodeling of church buildings, primarily
Forbes Hall and Religious Education classrooms.
Should you have questions you know in advance that you would like addressed, please e-mail them to the Congregational Concerns Sub-Committee of the Building Committee
c/o (Chair) Pat Parkerton
Phase 1:
The Cottage: complete.
Phase 2:
New Building: A new single story building with two classrooms will be built on the northwest corner of our property.
Open Space: There will be a separate play area for children between the new classrooms and the cottage. A lower courtyard off Forbes Hall will be connected by stairs and ramp to a long courtyard north of the sanctuary.
Forbes Hall Layout: The social hall, kitchen, and restrooms will be renovated, and the second floor classrooms will be combined into four larger classrooms.
Accessibility: All levels will be connected by ramps or an elevator while improving the space ‘flow’.
Parking: There will be seven parking spaces off the alley, which will not require a new city “parking variance”.
Landscaping: We will install pavers and plant the north side yard and front yard of the Cottage to the Anderson Courtyard. Drainage from the site will be improved. We will use the Santa Monica City $20,000 grant for water conserving landscaping.
Conditional Use Permit: We do not expect the city to require a new building permit.
Phase 3:
Sanctuary: Expansion of our sanctuary will be deferred.
2008 Tentative Schedule: (Depends on timely church actions and city approvals):
February 10 - Congregational Meeting to Approve Revised Plans
February - City Review of revised plans for compliance with 2007 CUP
March - Architectural Review Board Application: Landscape, Building Design
April - Submit Construction Drawings for Building Permit
May - Architectural Review Board review and approval of Landscape Plan, Elevations, Materials Contractor Bids, Negotiation, Contract Signed
June 17 - Deadline: Obtain Building Permit
July - Construction Start on New Building
April, 2007
Report from the Transition Committee
The Transition Committee will be providing you
with a monthly report on the progress of construction,
effects on programs and services, and utilization of
space during Phase #2 of our Building Program scheduled
to begin October 2007 and to be completed April
2009.
The Blue House construction is scheduled for completion
this August. RE classrooms, church program
meetings, and community rentals will be moved to the
Blue House as much as is possible.
Demolition of Forbes Hall and the RE Classrooms is
to begin this October.
We will have a gigantic garage/moving sale in July
(church stuff only), which will be coordinated by The
Men’s Group. Volunteers for this activity are needed.
“Moving Day” to move materials from Forbes, RE,
17th Street into storage modules and the Blue House
will be in August — watch for this date as we will need
MANY workers to labor and be festive.
The members of the Transition Committee are:
Carol Kerr, Marv Pulliam, Catherine Farmer, Melinda
Ewen, Ron Crane, Steve Wight, Nancy Howell, and Carol
Agate.
Ask questions — make suggestions — help! — and
be patient.
— Ron Crane, Transition Committee Chair
December, 2006
Long-Awaited Building Program Begins
After
the groundbreaking ceremony in September, a construction contract to move and
rehabilitate the cottage at 1248 18th Street was signed on
October 24, and construction fencing was erected
three days later. This culminates long-term planning
that in a sense began in 1966, when the 17th
Street lot was purchased for future expansion.
Then, in the early 1990s, focus group meetings reached
a consensus to significantly improve church facilities.
A capital campaign was planned in 1999, launched in
2000, and extended in 2005 after building plans were
switched from 17th Street to the lot next door. Finally,
we have begun the procedures of bringing all of our
church facilities into the 21st century.
— Rob Briner, Historian/Archivist
(At right: a 7:30 a.m. client meeting with Turk O’Conner of the
T.H. O’Conner Company; David Sellman, Project
Manager; Carol Kerr, chair of the Building Committee;
and Alison Kendall, professional planner and
immediate past chair of the committee.)
July, 2006
Town Hall Meeting on Building Plans
At a town hall meeting on Sunday, July 30, at 11:30 a.m., the Building Committee
will present the latest word on our building plans. By then we anticipate
that the revised plans for our application to the Santa Monica Planning Commission
will be ready for congregational review.
At the May 21 annual meeting the congregation authorized the Board of Directors
to submit an application for revisions to our Conditional Use Permit to the
city. The following amendment was added to the authorization:
“. . . prior to submitting the application the Building Committee [will]
prepare a mailing with the plans and information about the plans, and hold
an informational meeting for the congregation . . . .”
This application is to modify plans for phase two of the building program,
which involves new classroom space and a social hall. We hope construction
can start as soon as possible after we complete the moving and renovation
of the cottage.
As those who attended the annual meeting know, there has been a change in
the earlier plans. The Santa Monica City Council imposed a condition that
we secure 12 nearby parking spaces to be available during all church operating
hours. Because of board concerns that we could not meet that requirement without
its impacting or eliminating our programs, we have redesigned the area to
conform to zoning regulations without the requirement that we obtain a variance.
The building committee looks forward to discussing those plans with you.
Please try to attend the meeting. If you are unable to, please contact Carol
Agate with your comments and feedback
January, 2006
City Council Denies Appeal and Approves Variance and Use Permit
On December 13, 2005, the Santa Monica City Council voted 4 to 3 to approve
our use permit and parking variance, adding a number of conditions regarding
parking during the week. The additional conditions include a requirement to
provide 12 spaces within 1000 feet of the church in a manner satisfactory to
the planning staff. Additional requirements would add a monitoring provision
to assure the parking was provided, and that the parking was provided through
a formal lease.
Councilmembers expressed concern about assuring that the parking secured would
not already be required by the lots’ owners. A brief comment from Councilmember
Bloom just before the vote created some confusion about the time period during
which the parking would be required. Leaving the meeting, Councilmember Katz
reassured us that it did NOT mean the church would need to provide overnight
parking. The intent of Bloom’s remark seemed to be to require the parking Monday
through Friday evenings, rather than simply requiring activities to be restricted
if the 12 offsite spaces were not provided.
At the outset of the hearing, the church presented a letter reporting that
it had obtained approval from the Board of Elders of the Seventh Day Adventist
Church at Arizona and 19th Street to enter into a parking agreement with us.
Under the agreement, the church could use 12 spaces in the Adventist church
lot off 19th Street from Monday through Friday from 6 to 9:30 p.m. In addition,
the church proposed that if the council wished additional assurance that there
would be no increase in activity causing greater parking demand associated with
the church project, we would agree to either provide the parking or limit activity
to current levels. Chris Harding, pro bono attorney for the church, also submitted
a letter describing a federal statute known as the Religious Land Use and Institutionalized
Persons Act and its relationship to the church project.
Throughout the discussion, the fate of the church project seemed to be in jeopardy.
Councilmember Genser questioned why the church would propose to provide additional
parking, if we do not intend to increase activity. Building Chair Alison Kendall
responded that the proposed evening parking was to address neighborhood concerns,
but that the new space was to address the needs of the church’s Sunday programs,
but no increase was anticipated in activities during the week. She explained
that Sundays are the only time when the church facilities are fully used. She
noted that city parking requirements assume each room is fully used all the
time.
Additional discussion focused on the variance findings, and whether the church
could provide the 12 parking spaces on site. Planning Manager Amanda Schachter
explained that the lot and existing buildings made underground parking unfeasible.
Councilmember Genser described how the church could roll the house into the
street and leave it there while an underground garage was excavated, and then
roll it back into place. Grumbles from the crowd suggested most of the neighbors
thought this would not be a great way to address their parking problems.
A motion to deny the appeal and grant the approval was made by Herb Katz and
failed to find a second. A counter proposal by Ken Genser to grant the appeal
was made. Ultimately, Councilmember Richard Bloom moved to deny the appeal with
the staff recommendations, but adding the condition requiring an additional
12 spaces within 1000 feet of the church in a manner that is satisfactory to
staff. Voting yes to grant the church approval were Councilmembers Bloom, Holbrook,
Katz and Shriver. Voting against the motion, and thus to grant the appeal, were
Councilmembers Genser, McKeown and O’Connor.
The next step for our Building Committee is to make final adjustments to the
building plans and prepare a phasing plan. As soon as the city planning staff
clarify the parking requirement, the church intends to secure the parking agreement.
The committee will then submit construction drawings for first phase of construction
for building permit review. With good luck, relocation of the house and its
renovation could begin within a few months.
— Alison Kendall, Building Committee Chair
November, 2005
Council to Consider Our Building Variance November 22
The Santa Monica City Council will consider an appeal of the Planning Commission’s
unanimous approval of our Conditional Use Permit and Parking Variance on November
22. Please plan to attend, speak, or wear a badge to show your support of our
longdelayed plans to upgrade our facilities.
— Alison Kendall, Building Committee Chair
October, 2005
Church Works on Parking Ideas, but Delays will Cost More Money
Despite unanimous approval from the Santa Monica Planning Commission, the church’s
application to improve its Sunday school, office, and church facilities has
been delayed by an appeal filed by a neighbor who lives in the 1300 block of
18th Street. The appeal addresses the parking variance, and it mentions "lack
of parking spaces on proposed construction site" and "neighborhood needs parking."
After agreeing to a November 8 date, the appellant recently notified the Santa
Monica city staff that he will not be able to attend on that day, further delaying
the appeal.
The parking requirement for the four-phase renovation project is a total of
15 spaces, of which three are proposed to be provided off the alley. Unfortunately,
providing 15 spaces would take up most of the lot, and require removal of the
old house at 1248 18th Street. By contrast the shared parking arrangement we
have with UCLA provides over 200 parking spaces without requiring demolition
of the Craftsman house.
Meanwhile, the Building Committee has been investigating parking issues and
options. Alison Kendall and Marie Kashmer-Stiebing met recently with Jean McNeil
Wyner, Community Liaison for UCLA, who was encouraging about extending the hours
and days during which the church uses the garage. Possibilities include a longer
period on Sunday, Saturday weddings, and evenings when larger groups sometimes
meet in the church, as long as we continue to pay for an attendant to let people
with UUCCSM parking passes in and out of the garage. On September 13 the board
agreed to add an attendant at the UCLA garage on Monday evenings and to require
the large group meeting on that evening to cover the cost and issue meeting
attendees parking passes.
Although the majority of members who drive to church have been parking in the
garage, according to a June 2005 survey, the number could be improved to nearly
95%. Thus, the church is launching a campaign called "Good Neighbors Park
in the Garage." On September 18 parking passes will be handed out with
the order of service and a reminder will be included in announcements at both
services. Greeters will make a special effort to let visitors new to the church
know about parking in the garage. Building Committee members Keith Ludowitz
and Greg Wood are jazzing up the parking pass with additional information and
“Ten Reasons to Park in the Garage.” So improve your karma, decrease our neighbors’
parking hassles, enjoy a brief walk, and a cool and clean car — park in the
garage and help us build a better church and neighborhood.
Meanwhile, construction costs continue to climb. As a result we have to stretch
out the time frame for our building project. Rather than three phases, we are
now expecting four, with the final north wing of classrooms not expected to
be constructed until well into the future. With current capital funds, we hope
to be able to relocate the house, build the nursery and enlarge a few of the
existing classrooms in a short wing along the alley. Renovation of the sanctuary
and the north wing may have to wait until we can raise more funds.
— Alison Kendall, Chair, Building Committee
Thanks to All Who Helped Us Reach the 3/4 Mark in Our Fundraising
Kudos to the Capital Campaign canvassers: Rob Briner, Shirlee Frank, Bob Dietz,
Don Jameson, Jeff Greenman, Laurel Bleak, Gretchen Goetz, Natalie Kahn, Steve
Paddock, Arvid Knudsen, Judy Federick, Kris Langabeer, Karen Canady, Marv Pulliam,
Dan Kegel, Nels Hanson, Michele Pritchard-Lane, Diane Fletcher-Hoppe, Ellen
Levy, Greg Wood, Ren Renshaw, Jennifer Westbay, Florence Chapgier, Jim Cadwell,
Ed Hession, Dave Hallinan, Shannon Murphy, Beth Rendeiro, Debbie Fryman, Dan
March, Greg Poirier, Dan Teplitz, Leslie Reuter, and all of the “Lemonade Sunday”
participants. You have helped us reach the three-quarter mark in the 2005 campaign.
We are at $750,000 and counting.
Kudos to our congregation: You have been gracious and generous in meeting our
$25,000 matching grant and approaching our $1,000,000 campaign goal. You have
been especially generous in this, our second Capital Campaign. We are realizing
our first choice — continuing our church on the property next door to us. We
have more to do. We are still getting questions, such as: “Why haven’t I been
called about the Capital Campaign? I want to pledge, too.” “Have we raised enough
to complete the building project?” “How can I help in the rest of the building
project?”
If you are one of those not yet contacted or if you have any questions, please
speak with Ofelia Lachtman, Carol Kerr, or
Ron Crane.
— Ron Crane, Chair, Capital Campaign
September, 2005
Planning Commission Approves Project, but Appeal to City Council Means a Delay
On July 20, shortly before midnight, the Santa Monica Planning Commission unanimously
approved our application for a Conditional Use Permit and Variance. Many church
members came to express their support by wearing yellow stickers saying, “I
support the UUCCSM Building Project.” Many members spoke to the commission as
well, including YRUU members Amelia Harati and Emily Hero, who presented “Ten
Reasons We Need New Religious Education Classrooms,” including, “When the kids
do yoga in class, they can only do the folded up positions.” Many letters in
support of our application were received from community organizations that have
been assisted by volunteers and donations from our church, including Step Up
on Second, Ocean Park Community Center, and Westside Food Bank.
Unfortunately, the Commission’s approval was later appealed by Blair Calderhead,
a neighbor who lives in the 1300 block of 18th Street. The appeal will be heard
by the City Council, which will decide whether or not to uphold the Planning
Commission’s decision. We have not yet received a date for this council hearing,
which will delay our project by at least two months. The appeal and attendant
delay is a big disappointment to the many people who have been working for so
long on improving the church facilities.
Several neighbors spoke in opposition to the parking variance, and expressed
concern that the new space would impact on-street parking in the neighborhood.
Building Committee Chair Alison Kendall explained that the new RE classrooms
will accommodate existing Sunday school classes, and that programs on other
days of the week are not expected to increase. The church has had an agreement
with Santa Monica Hospital to use their parking at Arizona and 16th since 1988,
though the church and Forbes Hall were built before any parking requirements.
The parking garage generally has about 40 to 50 cars from church attendees
on a typical Sunday, and has space for hundreds more. The parking variance allowed
the 12 parking spaces required to provide the new classrooms to be provided
through the off-site garage space and the Parking Impact Reduction Plan the
church approved in May. This plan asks all church users to encourage carpooling,
walking, biking or transit use to reduce neighborhood-parking impacts. In addition,
three on-site spaces off the alley will be provided by the project. Special
thanks go to members of the Building Committee for help in preparing for the
meeting.
— Alison Kendall,
Chair, Building Committee
See the July 20 Hearing
An archived streaming video of the July 20 Santa Monica Planning Commission
hearing on our building project can be viewed on any personal computer at any
time by following the following easy steps:
1. Google “City of Santa Monica" and select the city's official home page
2. Under “City Hall" click on “Public Meeting Netcast"
3. Select “Video Archive of Planning Commission"
4. Select “Commission Meeting July 20, 2005"
5. In the drop-down menu under the video screen, go to and select “Item 10-A"
6. After a buffering delay, the video will automatically start at the beginning
of 10-A
7. Now you can listen to and watch the entire 2-hour hearing.
August, 2005
On July 20, the Santa Monica Planning Commission approved our construction
plans (see details above).
July, 2005
Planning Commission to Hold Critical Hearing About Our Church Building Project
on July 20
On Wednesday, July 20, the Santa Monica Planning Commission will review our
application for a Conditional Use Permit and Variance. The two permits are needed
for us to build new Religious Exploration classrooms to the north of Forbes
Hall and to convert the old house to offices so we can expand the size of our
sanctuary. We are urging all members, friends, and supporters of the church
and its project to write to the Planning Commission or to attend to express
their support in person.
If you choose to write, please send your letter by June 30 to the Planning
Commission, Attention Roxanne Tanemori, Associate Planner, Planning & Community
Development Department, City Hall, 1685 Main Street, Room 212, Santa Monica,
CA 90401. Note that you are writing regarding Variance 05VAR006 and Conditional
Use Permit 05CUP004 for 1248-1260 18th Street by the Unitarian Universalist
Community Church of Santa Monica. Please note whether you are a member, friend,
neighbor, or supporter of the church. Note any other roles you have in the Santa
Monica community, including living in Santa Monica, owning a home or business,
or volunteering with local community groups.
Here are some key points you may want to include: The sanctuary was built 75
years ago, in 1930, and the social hall in 1961. Both were built before on-site
parking was required. Recognizing the need to accommodate parking for members
on Sundays, our church has a longstanding agreement to use UCLA’s garage at
16th and Arizona. On a typical Sunday, 40 to 50 members park their cars in this
structure to avoid crowding on local streets. The congregation has approved
a Good Neighbor Parking Impact Reduction Plan to assure that all groups using
church facilities work to reduce noise and parking problems for our neighbors.
Be sure to note if you regularly walk, bike, carpool or park in the garage.
The proposed project preserves the Craftsman bungalow on its original site,
moving it forward and away from side property lines to conform to setbacks.
The house would be used for offices, while a new classroom wing would be located
behind the old house, with open space between the two buildings. The plan preserves
the scale and character of the existing buildings, including our historic sanctuary.
Be sure to talk about how important the project is to you, the fact that the
church has been working on the project for six years, and your support for the
current plans.
If you can, join us on July 20 to deliver your message in person. The location
is City Hall on Main Street and the time is 7 p.m.
— Alison Kendall, Chair, Building Committee
June, 2005
Our Building Fund Received..
...a grant of $25,000 from Spirit Level Foundation, a group of UUs in San Diego
who support worthwhile church construction projects.
April, 2005
Don't Park on Street; You Could Win a Raffle Ticket
The Building Committee met with neighbors of our church on March 13 to answer
any questions about our building project. We blanketed the neighborhood with
invitations, and had six neighbors attend, all of them residents of 17th, 18th
or 19th Streets. We soon learned that they had three issues on their minds:
parking, parking and parking.
The neighbors acknowledged that much of the problem in the neighborhood comes
from employees at the car dealerships and visitors to the nearby hospital and
medical offices who park on the street rather than pay high parking prices.
In addition, many housing units in the neighborhood lack onsite parking for
residents. Our church contributes to the lack of street parking at our busiest
times, especially Sundays and Monday evenings when a large group rents Forbes
Hall. We can help to reduce our impact on an already difficult situation by
carpooling with others to events at the church.
We have a long-standing agreement with UCLA that provides us with access to
their garage at the corner of Arizona and 16th Street from 8:30 a.m. to 2:30
p.m. every Sunday. These hours can be lengthened with advance notice to accommodate
our occasional Sunday afternoon events. All you need to do is pick up a light
blue parking permit from the front office, place it on your dash, and have the
attendant let you in. We are distributing copies of the parking pass at services
to make sure everyone has a copy.
If you need to drop off food, young children, or older or disabled people who
have difficulty with the walk from the garage, please use the spaces along Arizona.
We have asked the City to allow one of the spaces on Arizona near Forbes Hall
to be designated a yellow “drop off zone,” but until the curb is painted, we
will need to try to keep this area free for dropping off on Sundays.
Another great way to get here without parking hassles is on the Big Blue Bus,
Santa Monica’s award winning bus system. Our church is located right between
line 2 on Wilshire Boulevard and lines 1 and 10 on Santa Monica Boulevard. We
have posted the bus map and schedule in the lobby of Forbes Hall, along with
a supply of schedules for these lines. The fare is 75 cents and is only 25 cents
if you are at least 62 years old. Check bigbluebus.com
for further information.
My favorite way to arrive at church is on foot or on a bike. If you’ve been
looking for an excuse to take a walk or a bike route, what better time than
Sunday morning? Walking to church gives you a chance to relax and enjoy the
gardens, stop in for brunch, and do your errands. We have a bike rack in the
back yard of 1248 and are looking into installing one in Anderson Courtyard
to provide a convenient place to lock your bike. Don’t forget to wear a helmet.
Bike route information is posted with the bus schedules in Forbes Hall.
For the next few months we will be offering special incentives for using our
remote parking, carpooling, walking, biking or taking the bus to church. As
you arrive at the church, tell us your “good neighbor” effort and you will get
a raffle ticket good for prizes at the end of the month. You’ll also be helping
us document our good neighbor travel behavior for our follow-up meeting with
the neighbors and our public hearing with the Planning Commission later in the
spring. So let’s not forget to “walk the walk” on our way to church, as well
as within.
—Alison Kendall, Building Chair
March, 2005
Our Building Project Application is Submitted to Santa Monica
By the time you read this, the Building Committee will have submitted our application
to the City of Santa Monica for a conditional use permit to remodel and expand
our classroom and office uses onto the adjacent lot at 1248 18th Street. The
use permit will include permission to move the existing house about 14 feet
closer to 18th Street, and about five feet further from the side property line.
A variance is also needed to allow most of the parking for the church expansion
to be provided off site, including continuing use of the nearby parking garage
during Sunday services.
The city's review of the application will have comments by building, fire,
transportation, and other staff; an analysis of potential impacts on historic
resources from the project; preparation of a staff report, and scheduling of
review by the Planning Commission, probably in late spring.
We will be holding a community meeting in March to explain the project to area
neighbors and to discuss any questions or concerns they have. Please contact
Alison Kendall if you live in the neighborhood or want to help with this important
meeting. The Capital Campaign Committee and Building Committee have begun to
work to make sure we can raise the remaining money needed to undertake this
important project. Together, the two groups will be maintaining the “Building
Our Dream” bulletin board in Forbes Hall to help people stay informed about
our progress. Please stop by after Sunday services to look at the bulletin board.
There is generally a member of one or both committees there to answer your questions.
With our architect, Ralph Mechur, we are beginning to prepare more detailed
plans for the building project and to develop plans for structural, plumbing,
and electrical systems. There are also several urgent repair projects to the
sanctuary roof, electrical system, and front doors, which are likely to need
attention before the building project begins. Rod Lane and Steve Paddock, Building
Committee members with extensive construction management experience, are working
with Marie Kashmer-Stiebing, Church Administrator, to make sure these repairs
are coordinated with the larger building project.
The committee has been working hard this month on ideas for the central courtyard
and other open spaces, and on ways to unify our church campus and its variety
of architectural styles. Come check out the bulletin board and give us your
feedback.
— Alison Kendall, Building Committee Chair
February, 2005
Building Committee Prepares Applications for City Agencies
The Building Committee has been hard at work preparing the plans and application
materials for submission to the City of Santa Monica. The application materials
include a request for Development Review and a Conditional Use Permit to remodel
our existing facilities at 1260 18th Street, adding a new religious education
wing to Forbes Hall at the back of the new property at 1248 18th Street, and
moving the house forward and remodeling it for use as office space. We are also
requesting a variance for a reduction in on-site parking and use of off-site
parking facilities very similar to the request approved by the Planning Commission
last year. Alison Kendall, chair of the Building Committee, is completing the
necessary application materials with our architect, Ralph Mechur, and our pro-bono
land use attorney, Chris Harding.
With plenty of committee input on the design, the architect is finalizing all
the drawings required by the city, and we hope to submit the application in
early February. We will be holding a community meeting sometime in March to
describe our proposal and offer discussion about concerns that our neighbors
might have.
We hope to have a Planning Commission hearing in the spring. Remember, however,
that our previous application (about the 17th Street property) had been deemed
complete in October 2003, yet the hearing about that application was not held
until early March 2004, so we are likely to encounter delays this time around
as well. After Planning Commission approval we will need to go through Architectural
Review Board approval, and then prepare and submit construction drawings for
building permits. We hope to expedite the house relocation and remodeling to
give us usable space before remodeling Forbes Hall and building the new wing.
Expansion of the sanctuary will be the final phase.
The sale of our 17th Street parcel netted over $1 million, a major start to
our new capital fund, which was depleted by the purchase of the lot at 1248
18th Street. A new capital campaign is expected to start soon to close the gap
between our current funds and the anticipated total amount needed for all three
phases of construction. We are starting to work with our architect and the contractor
we had selected for the 17th Street project to refine our original planning
level estimate of $1.8 million.
The Building Committee meets every other Monday at 6:30 p.m. This month’s meetings
are scheduled for Monday, February 14, and Monday, February 28. Please contact
Alison Kendall or Marie Kashmer-Stiebing, Church Administrator, to confirm meeting
dates.
—Alison Kendall
January, 2005
We Sell the 17th St. Property for $1.1 Million with a 15-month Leaseback
at $1 Per Month
After having listed the 17th St. property for sale in October, we closed the
sale of the property on December 14 for a purchase price of $1,100,000. Even
after our first buyer for the property walked away from the deal, there was
a great deal of interest in the property and our broker fielded over 200 calls.
We received several confirmed offers before settling on a final purchase agreement.
The net cash to the church, after paying closing costs and commissions, is expected
to be approximately $1,030,000, although a small portion of that purchase price
is being held in escrow during our lease term. A total of $995,023 was wired
into our bank account on December 14.
The agreement specifically includes a leaseback of the 17th St. property to
the church for 15 months at $1 per month. We might be able to extend the lease
longer (assuming we still need the space) if the developer is not yet ready
to proceed with construction at the end of the 15 months. Based on estimates
from some of the bidders, the value of this lease to the church is approximately
$45,000 (based on a monthly rental rate of $3,000 per month).
I am so pleased that we were able to sell our very valuable asset at such a
good price. As previous newsletter articles have indicated, we paid approximately
$1,250,000 for the 11,000 square foot lot on 18th St. (which is about 3,500
square feet bigger than the 17th St. property), so the result for our 17th St.
property is really excellent. We also did much better than some earlier estimates
of value in the $600,000-$700,000 range. We ultimately sold the 17th St. property
for about $146 per square foot, which is actually higher than the per square
foot cost of the 18th Street property (coming in at $114 per square foot).
My thanks again to Pat McGuire and Warren Mathews for serving on the special
committee that helped review offers and strategize about the property, and for
the support of the board over the last two months. I hope everyone enjoys a
happy and healthy new year.
—Carol Kerr, President
As We Refine Our Building Plans We Consider Architectural Styles
The Building Committee has been working with our architect to refine the plans
to reflect all the input on specific program needs received at our November
6 “Refine the Design” workshop for congregation members. We have also begun
to work on the challenge of determining the architectural style of the new building,
and how to integrate it with our existing buildings.
The consensus has been that among the many styles on our campus, the simple
elegance of the sanctuary is the style that we should take our cues from. Some
modifications to the exterior of Forbes Hall to make it more compatible with
both the sanctuary and new building are being studied. We should have a new
set of design drawings posted in January on the “Building Our Future” bulletin
board.
As soon as the full set of elevations, sections and other drawings is completed,
we hope to submit them to the City of Santa Monica. The application will include
a Conditional Use Permit for use of our new property for church activities as
well as the new construction and relocation of the old house.
—Alison Kendall, AICP, Building Committee Chair
December, 2004
Architect Refines Building Plans After Members Discuss Designs
On Saturday November 6, the Building Committee hosted a “Refine the Design”
workshop for members of the congregation to review the latest plans and to comment
on them. About 20 members of the congregation participated, many of them longtime
active members with a good understanding of the space needs for the many activities
that occur in our church spaces.
Facilitated by our architect, Ralph Mechur, and Building Committee members,
our discussion began with the topic of RE facilities, including the location
of storage, preservation of the room 4 mural, provision of movable partitions
in upstairs rooms, and other issues. A discussion of open space generated ideas
for developing a flexible play area for older kids, a fenced area for younger
children, and a long courtyard providing direct access from the new kitchen
and Forbes Hall to Anderson Courtyard to be used for outdoor events. The day
concluded with discussions about the sanctuary area. Many additional topics
were discussed and many participant comments noted on the plans.
The architect is currently refining the plans in response to comments emerging
from the workshop. We will be updating the “Building Our Dream” bulletin board
in Forbes Hall with the latest set of plans as changes are made. We urge members
of the congregation to post their comments on the message board or to e-mail
the Building Committee Chair.
Additional design changes are likely to occur as we consult with the Santa
Monica city staff and start to look at the cost implications of our design.
We will need to remain flexible, collaborative, and able to prioritize as we
develop a design that meets our needs and allows us to move toward our dreams.
The Building Committee is now meeting every two weeks on Monday evenings at
6:30 p.m. in 1248 18th Street. If you would like to attend, please contact me
by e-mail to confirm the next meeting date.
—Alison Kendall, Building Committee Chair
November, 2004
Come Help Refine Our Building Design, Saturday Afternoon, Nov. 6, Forbes
Hall
Come help refine our building design Saturday afternoon, Nov. 6, Forbes Hall
On September 19 our congregation voted overwhelmingly to proceed to develop
an application for the Planning Commission based on Option M-1. This option
includes a few key features:
• Use the old house for administrative offices and library.
• Build new two-story structure for RE classrooms behind house and connect to
existing rooms on second floor of Forbes Hall.
• Create a central courtyard for RE play area, coffee hour and other uses.
• Expand the social hall to the north; provide new kitchen and accessibility
improvements.
• Expand sanctuary into area used by offices and nursery.
Before submitting the plans, we would like to review them with the congregation
in order to think about any revisions that would better accommodate our activities.
To do so, we invite all members to attend a design workshop on November 6. We
will spend an hour on each of the major areas of the church and the proposed
project. Come for the whole afternoon or just for the area you are most interested
in.
Here’s a tentative schedule:
12:30 p.m. – Introduction to Design
1 p.m. – RE classrooms in new building and second floor of Forbes
2 p.m. – Outdoor areas and parking
3 p.m. – Social hall expansion and new kitchen
4 p.m. – Sanctuary expansion; administrative offices/library
5 p.m. – Wrap-up; discussion of next steps
—Alison Kendall, Chair, Building Committee
17th Street Property Update -- Escrow Cancelled
Unfortunately, the buyer of the 17th Street property cancelled escrow on October
27 pursuant to his inspection contingency. The purchase agreement gave the buyer
until October 30 -- 15 days from acceptance -- to complete all inspections and
due diligence on the property. (This is basically a "free look period"
because the buyer can give any or no reason for not proceeding and recover the
entire deposit.) No specific reasons were given for the cancellation. Our broker
is highly confident that we will get back into contract very quickly on the
property given the other strong offers received and continued interest in the
property -- even after we signed the purchase agreement. Although obviously
disappointing, this setback is not unusual in the real estate world, our pricing
is right for the market, andthis should not be seen as anything more than a
temporary delay!
-- Carol Kerr, Board President
October, 2004
Congregation Votes 108-34 to Proceed with Plan; Sell 17th St.
In a crowded sanctuary on Sunday, September 19, the congregation as a community
voted to move forward on development plans outlined in the Building Committee’s
M-1 design. It then voted to renew the capital campaign to raise additional
money to pay construction costs. Finally the congregation voted to authorize
the immediate sale of the 17th Street property.
In a respectful, orderly, and issues-oriented special congregational meeting,
over 130 members heard and spoke about maybe the most important choices to be
made in many years by the congregation.
The final vote on the first motion, to authorize the Building Committee to
“proceed immediately with the development and submission of an application”
on the M-1 design to the Santa Monica planning commission, was nearly unanimous.
But before the vote was taken, there was plenty of discussion and questions
to the Building Committee. The M-1 design would include enlarging the sanctuary,
adding RE classrooms on the 18th Street property, and moving the existing house
forward and refurbishing it as church office space.
Alison Kendall, the chair of the committee, outlined the steps leading up to
the congregation’s vote on the M-1 design. These steps included three workshops
since the purchase of the 18th Street property in March, surveys of church members,
research, and conversations with city, community, and UU Association officials.
She also stated the urgent needs of the congregation for better RE facilities
and for a larger sanctuary.
Alison said that although the M-1 design may be a compromise based on financial
and time constraint issues, it was a good plan that had fewer constraints than
building on the 17th Street property. Keeping the old house on 18th would remove
time-consuming preservation issues. She said that after congregation approval,
the Building Committee could fine-tune the design and work with interested church
groups to make sure their needs were met.
Many of the questions raised centered on the vision for the church, what size
congregation was desired (550 to 600, acknowledging that more could not be fit
on the property in Santa Monica), open space for the children and for the congregation
(an important consideration), and whether keeping and moving the old house was
a good idea (the house would be brought up to code and the rear rooms removed,
making the house a good space for church offices).
Warren Mathews presented a financial picture that showed that the church did
not have a lot of money currently available to support capital construction.
He also stated that the budget for 2004-2005 anticipated a $13,000 budget deficit.
He had indicated earlier that it would be difficult to get loans for construction
when the church could not show that it was consistently meeting its current
expenses.
The second motion, to authorize the Board of Directors to “renew the capital
campaign to raise construction funds from the members and interested friends
of the Church…” was also almost unanimously approved, with little discussion.
The final discussion, to sell the 17th Street property, brought out the strongest
differences in opinion. Beginning the discussion, Richard Boothe noted that
real estate prices may dip, even in Santa Monica, and that the church could
lose out by delaying a sale. Rob Briner wanted to hear discussion on ways to
both keep the 17th Street property and proceed with the M-1 development. Ray
Goodman, Bonnie Brae, and Rebecca Crawford strongly opposed the sale. They felt
that the congregation was rushing into a vote on the property, that there was
enough of a possibility that loan guarantees could be developed, and that the
church was ignoring and would forever lose the benefits that keeping the 17th
Street property would bring. They suggested that waiting a little longer before
selling the property would cause no problems and would allow time to pursue
fund-raising and loan possibilities.
Some of the congregation left before the vote on the motion, but when tallied,
the vote was 108 in favor of selling the property, 34 opposed, and 1 abstaining.
The vote included a number of absentee ballots.
The church now has a focus for its next steps, plus a lot of hard work still
to do. And after that a lot of construction dust.
– Nels Hanson
September, 2004
Vote on September 19!
What should we do with the house next door? Should we sell the 17th Street
lot? These and other questions will be discussed and voted on at a congregational
meeting on Sunday, September 19. The purpose of the meeting is to (1) approve
preliminary building plans/direction for the new 18th Street property based
on a recommendation from the Building Committee, and (2) vote on whether or
not to sell the 17th Street property to help finance the approved building plans.
(See full agenda and, if you're still
undecided, arguments for and against
the sale.) Lunch will be available before the meeting. At least 79 members must
be present for a quorum.
August, 2004
Our New Building Committee Leader Wants Us to "Sustain the Momentum"
“In planning jargon,” says Alison Kendall, “I’m a Green New Urbanist, someone
who tries to bring different uses together and encourages walking and human
action. My design philosophy involves exploring both community and individual
needs, integrating nature and environmental concerns, and expressing the unique
history and culture of the place.”
Alison, our new Building Committee chair, joined our church and its Building
Committee last fall, shortly after she, her husband, Francois Bar, a professor
of communication at USC’s Annenberg School, and their children, Nick, 14, and
Jessie, 10, moved here from Palo Alto. Nick just completed our Coming of Age
program and starts ninth grade at Samohi this September. Jessie will be a fifth
grader at Franklin Elementary School.
Alison, who has graduate degrees in architecture and planning from Berkeley,
owns a planning and design business in Santa Monica, offering services to cities
and private landowners. “I’ve had my own business since 1996. Most of my work
to date has been in the San Francisco Bay area, where I prepared a plan for
a 20-block area south of downtown Palo Alto, including a park, childcare center,
historic buildings, single family housing, condo housing and affordable family
housing, and other uses. I managed planning for converting Treasure Island Naval
Station into residential and recreational use and was San Francisco’s coordinator
for converting the Army base at the Presidio of San Francisco into a national
park.”
She has also worked on plans for San Diego and Sacramento, helped landowners
with master planning for their properties and planning approvals, and managed
the eight-person development review staff for the City of Mountain View in Silicon
Valley. She’s renovated three houses and worked on historic preservation and
renovation plans for many more as a building designer in St. Louis and in Italy.
Born in Canada of Australian parents, Alison grew up in Pennsylvania “and moved
to California as soon as I could, at 18 to go to Berkeley,” she says. “I enjoy
travel and new experiences and unconventional people. I’ve been a Unitarian
Universalist since age 14.” The Kendall-Bar family likes living in Santa Monica.
“We’ve met lots of creative and friendly people here through the church and
the schools. I’m impressed at the generosity and commitment to social justice
we’ve found here.”
As a member of the UUCCSM Building Committee, Alison helped get Santa Monica
Planning Commission approval for the 17th St. project. “Although it is disappointing
that we are now further away from starting construction, I’m excited about the
new options we have with the house next door on 18th St. We can now provide
more spacious classroom space, improve the social hall, enlarge the sanctuary,
and link all these uses with beautiful, usable outdoor space.
“We are studying options for moving and renovating the old house, which has
lots of great detailing and craftsmanship,” Alison continues. “The toughest
challenge is our shortage of money. We need to be realistic and to make tough
decisions in order to see this project through to completion.
“There are many, many people who have given a great deal of time and money
to get us to this point in our building process. Our space needs are critical
and despite the vitality and progressive nature of the church’s programs, our
facilities are dilapidated and inadequate.
“I hope we can sustain the momentum we have established so that we can begin
to improve our facilities within a year,” says Alison. “We need to make critical
decisions over the next few months about reusing or moving the old house, selling
the 17th St. lot, and raising over $1 million to move ahead.”
—Paula Bernstein
July, 2004
The Building Committee Reports on June Activities and Town Hall
The Building Committee held two workshops on June 2 and June 19 to receive
comments on the building options described in the June newsletter and to explore
options to finance construction since acquisition of the 18th Street parcel
has absorbed most of the capital fund. The June 2 participants indicated strong
interest in either option M-2, where the old house is used for administrative
offices and a two story RE building is constructed behind and for option R-1,
which removes the house in order to build a new social hall and RE classrooms.
Participants indicated strong interest in funding either option with a combination
of another capital campaign, a major loan, or sale of the 17th Street parcel.
The committee has been taking a closer look at the condition of the house and
possible costs of moving and renovation, including requesting preliminary estimates
from Alpha Construction and additional information on costs to address termite
damage, asbestos, and structural problems. Collecting and analyzing this information
will continue into next month. The preliminary information suggests that the
costs of moving and renovating the house will be slightly less than a similar
amount of new construction, although it will not address the specific program
needs quite as well.
—Alison Kendall, Building Committee Chair
June, 2004
Building Committee Provides Building Options Overview
The recent purchase of the property at 1248 18th Street, adjacent to the existing
sanctuary, has opened up new and exciting possibilities for expanding and upgrading
our facilities. Unfortunately, at a cost of $1.265 million, it has also absorbed
most of the capital improvement fund which had been built up to begin construction
of new religious education classrooms on the 17th Street lot, to expand the
sanctuary, and to make access and code-related improvements to Forbes Hall.
Ironically, the purchase of the new parcel could move us further away from
urgently needed improvements to our facilities, unless we move quickly to make
some key choices and find a substantial amount of additional money to fund construction.
This article summarizes the major options, provides preliminary cost comparisons,
and explores the advantages and disadvantages of the options to be discussed
at upcoming meetings June 2 and 19.
Options based on March meeting explored
Since the church closed escrow on March 31, the Building Committee has been
studying options for use of the newly acquired property, upgrading the sanctuary
and Forbes Hall, and use or sale of 17th Street lot. The tour of the house and
town hall meeting held March 21 generated a wealth of ideas; more ideas have
emerged as members explore the back yard now accessible from Forbes Hall and
post their ideas on the alcove bulletin board. Building Committee members are
considering these suggestions and drawing on their collective expertise in real
estate, development, planning, and landscape and architectural design, as they
explore options for all of the church properties with our architect, Ralph Mechur.
Building program priorities defined
Over the past four years, the congregation has defined three major priorities
building priorities. All three remain urgent:
1) Expand the sanctuary to provide less crowded seating for Sunday services
by relocating the administrative offices and nursery space.
2) Address accessibility and other code issues in Forbes Hall by providing
wheelchair accessible restrooms, elevators, and fire exits.
3) Provide adequate classroom space for the religious education program, including
nursery facilities, outdoor play space, and appropriately-sized classrooms not
provided in the current cramped second-floor facilities above Forbes Hall.
Planning Commission approved 17th Street
We currently have Planning Commission approval to expand the sanctuary, to
remodel into administrative offices the space upstairs from Forbes Hall, and
to build a new RE facility on 17th Street. Commission approval includes measures
to reduce church impacts on street parking. To actually build upon the 17th
Street lot and make the changes to Forbes and the sanctuary we would have to
obtain Architectural Review Board approval, prepare construction drawings, develop
a parking management plan, and obtain building permits.
The church could decide to launch a new capital campaign to proceed with the
approved 17th Street RE building project and essentially “land bank” 1248 18th
Street until additional capital funding makes development on that site possible.
In the interim, we can enjoy the open space behind the house and repair the
house for storage or offices. The approved RE facilities on 17th Street pose
safety issues and logistical challenges. The acquisition of the new parcel opens
the opportunity of locating the RE classrooms next door to the sanctuary, avoiding
the need for children to cross the alley, and creating a more compact campus
that will be easier to operate.
Estimated cost: $1,258,640.
Options for 18th Street properties are studied
In addition to the “17th Street option” approved by the Planning Commission
on March 3, the committee has developed three basic options focusing primarily
on the two 18th Street properties, to see how our current space needs can be
accommodated without using the 17th Street property. Each of these options would
allow the 17th Street property to be sold or leased to help finance construction
and upgrade on the 18th Street properties.
While elements of these options can be combined or modified in many ways, the
committee feels these three options represent a range of basic choices. Options
are intended to explore a range of construction costs and physical changes.
We have provided general “order of magnitude” cost estimates for renovation
and new construction. These estimates are very preliminary and do not reflect
detailed estimates of the cost of renovating the house or major alteration of
Forbes Hall, which will require further study once a preferred option is identified.
Options for reusing the 1248 18th Street house
There are two basic building
options for the newly acquired lot: keep it to be reused as offices or classrooms,
or remove it to be replaced by new construction. In order to maximize the area
behind the house for use as open space and RE classroom space, the committee
recommends that if the house is retained, it be moved about fourteen feet toward
18th Street. Renovating the house may cost almost as much as building new space,
and will limit options for new construction. But preserving the house would
win support from both neighbors and city officials, and might allow us to obtain
some flexibility on other requirements.
If the old house were removed, more extensive new construction would be possible,
including the possibility of both new RE facilities and even a new social hall,
along with up to 17 spaces per level in an underground parking garage. Removing
the house would require approval from the Landmarks Commission, which may find
the house eligible for protection as a historic resource, making removal difficult.
It may be possible to donate the house to be moved to another site, or to sell
its architectural features for reuse.
The floor plans on the following pages illustrate three land use options for
the campus. The text below summarizes the major options, their advantages, disadvantages,
and cost estimates. These costs do not purport to show what the actual costs
will be. They serve as a basis of comparing the various options.
Option M-1:Use house for offices
Phase 1: Move bungalow
closer to 18th Street and renovate for administrative offices.
Phase 2: Renovate and expand first floor of Forbes to the north, adding a new
kitchen. Build a two story, L-shaped building containing RE classrooms above
parking and ground floor nursery, classrooms, and play area
Phase 3: Renovate second floor of Forbes Hall for RE classrooms and other uses,
and connect to new RE classrooms to the north.
Phase 4: Expand sanctuary seating area, relocating nursery and offices.
Advantages: Seven new RE classrooms built behind house in early phases.
Good outdoor access for RE classrooms. Some of Forbes Hall converted to music
room. Administrative offices in house provide homelike setting and provide security
to campus.
Disadvantages: Only three parking spaces provided, one accessible.
Three classrooms above Forbes remain very small and narrow.
Estimated cost: $1,814,000.
Option M-2:Use house for RE classrooms
Phase 1: Move house
toward 18th Street and renovate for use as RE classrooms. Build single-story
nursery and two classrooms with adjacent play yards, plus two parking spaces.
Phase 2: Renovate and expand Forbes Hall, including the kitchen. Renovate second
floor above Forbes for administrative offices.
Phase 3: Expand sanctuary seating area, relocating nursery and offices.
Advantages: Fewest construction phases, minimal relocation of uses.
Three classrooms open directly to play yards. Lower construction cost for one-story
RE facilities. Lower costs for minor remodel of second floor above Forbes.
Disadvantages: Classrooms in house and back of lot are very small.
Administrative offices on second floor are hard to find, don’t improve campus
security, less pleasant. Only two parking spaces provided, one accessible.
Estimated cost: $1,472,500.
Option R-1: Remove house
Phase 1: Remove bungalow
and excavate site for underground parking. Construct about 17 spaces per level
of underground parking on new lot. Construct two stories of RE classrooms on
rear of new lot above parking. Construct new social hall, kitchen and meeting
rooms above parking.
Phase 2: Renovate and expand Forbes Hall for administration.
Phase 3: Major structural renovation of the second floor above Forbes for larger
RE classrooms, connect to new building.
Phase 4: Expand and renovate sanctuary.
Advantages: More attractive social hall with direct open space access
and modern kitchen, increased event rental revenue. RE classrooms in Forbes
are reconfigured. New, large RE classrooms with direct outdoor access. Administrative
offices on first floor are practical. Provides 17 parking spaces per level in
secure garage. Accommodates most growth in membership and programs
Disadvantages: Requires obtaining Landmarks Commission approval for
removal of bungalow. Underground parking is costly and disruptive to construct,
may be difficult to manage. Additional cost of constructing new social hall
and major renovation of second floor of Forbes Hall. More expensive and more
difficult to phase.
Estimated cost: $2,807,400.
Options for 17th Street
On March 3 the Planning Commission approved the construction of a new building
for RE classrooms and meeting rooms on the 17th Street lot. With 1248 18th Street
purchased just a few days later, RE programs housed adjacent to the sanctuary
and Forbes Hall would eliminate the dangers of children crossing the alley.
But to provide better space for the RE program without a long delay, we could
move ahead to build the approved RE facility on 17th Street. This option would
include expanding the sanctuary and could also include moving the offices to
the second floor above Forbes Hall.
At the March town hall meeting, a number of other options for the 17th Street
site were suggested:
• Sell the lot to help finance construction on the newly acquired parcel and
renovation of Forbes Hall and the sanctuary. Recent parcels of similar size
in the area suggest that the lot could be sold for about $800,000- 900,000,
most likely to a developer who could build five housing units on it under the
R-2 zoning.
• Build affordable housing on the site, perhaps a kind of Sunset Hall West
for seniors. Affordable and senior housing can be built at higher densities,
with lower parking requirements. However, the small, narrow lot (50 feet by
150 feet deep) makes sufficient parking extremely difficult to provide cost-efficiently.
The City of Santa Monica recently developed such a site with a lower land price,
and has said that it would not be interested in such project here.
• Hold onto the lot for future expansion needs. This is not feasible given
the cost of renovating the other facilities unless we can find a way to generate
income from the parcel with relatively low improvement costs.
Financial realities
The $1.265 million purchase price, including closing costs and broker’s commission,
came predominantly from about $770,000 raised from the capital campaign held
2001 to 2003, and $473,000 from the Morgan bequest. Even with about $284,000
in outstanding pledges to the capital campaign, we don’t have enough money for
the new construction we need to accommodate the building program goals.
Even the most modest reuse proposal – upgrades to the old house, new construction
behind it, and accessibility upgrades – is estimated to cost over $1.47 million
in improvements alone. This implies some combination of another major capital
campaign, a major loan, and sale or lease of the 17th Street lot. Sale of 17th
Street would substantially close the funding gap and allow us to move ahead
with options M1 or M2. Option R1 would require additional financing. In order
to move ahead to realize our dreams of better facilities, we need to engage
in an open discussion about these financial realities and choices.
Some evaluation criteria
These options represent a range of choices, and could be combined in various
ways to yield a “master plan” for our building program. Here are a few of the
key criteria for making our final selection:
• Net cost per square foot of new space including land purchase and sale after
2004.
• Net cost for renovation of existing space.
• Quality, proximity and practicality of administrative office space for staff,
ministers and volunteers.
• Quality of social hall and kitchen space, including adjacent outdoor space.
• Quality of religious education space: number of classrooms, shape/size, access
to play-yard, safety/access, toilet and changing facilities for infant/toddlers.
• Phasing options for capital campaigns and minimizing construction disruption.
• Options to preserve future flexibility or allow future growth.
• Possibility of upgraded facilities providing increased rental revenue. Next
steps: Over the next two months, the following key meetings are scheduled to
discuss building options. • Special town hall meeting on Wednesday, June 2,
at 7 p.m. in the sanctuary.
• Workshop on Saturday, June 19, from 1 to 3 p.m. at de Benneville Pines.
• Town hall meeting on Sunday, July 25, at 11:30 a.m. in the sanctuary.
— Alison Kendall, Building Committee
May, 2004
Back to the Drawing Board as Plans are Made for 18th Street
Ralph Mechur, architect for our 17th Street building project, is optimistic
about chances that the Santa Monica Planning Commission would approve our future
plans for the house next door to the church.
That house, at 1248 18th Street, a four-bedroom blue craftsman built in 1914,
was purchased last month for nearly $1,265,000, including closing costs and
broker’s fee. Plans for a new religious education building on 17th Street, across
the alley from Forbes Hall, have been shelved.
"It is exciting to think about expanding onto the adjacent property in
lieu of onto the 17th Street property," Ralph said. "Clearly, it provides
an opportunity to provide a more secure and integrated campus with more open
space. We will look at several concepts over the next few weeks." Renovating
the craftsman house will help preserve a part of Santa Monica’s history, he
pointed out, adding, "This, coupled with the possibility of providing staff
parking on the site should make the expansion an even stronger project for the
community."
The Santa Monica Planning Commission unanimously approved plans for the 17th
Street project at the first hearing on March 3. “The Santa Monica city staff
and the planning commission carefully evaluate projects for any potential negative
impacts on neighborhoods,” commented Ralph. “That the planning commission approved
the project at the hearing shows how important the church is to the community
and how reasonable the expansion project really is. They clearly understood
that the church’s goal is to remain in the community and to continue being a
communitywide resource in many ways.
“Returning to the planning commission with a project of similar scope should
receive the same support and approval” he added.
— Paula Bernstein
April, 2004
Our Church Made a Presentation to Santa Monica's Planning Commission
Building committee chair Barbara Kernochan made a report to the members
of the committee the day after the March 3 planning commission meeting:
Congratulations to us! Thanks to this team’s hard work, and with a lot
of help from friends and architects, our applications for a parking variance
and conditional use permit were unanimously approved at last night’s planning
commission hearing. All who were present came away, I’m sure, with the
sense that our congregation is truly heard and appreciated in our community.
The speakers waxed heartwarmingly eloquent about our good work, and even the
one neighbor who felt compelled to bring up parking problems did so with great
reluctance.
Bravo, and thank you, Barbara.
(The full text of the statements presented at the meeting is below.)
March, 2004
Statements of Judith Meyer and Barbara Kernochan to the Santa Monica City
Planning Commission
Judith Meyer:
I am Judith Meyer, minister of the Unitarian Universalist Community Church
of Santa Monica. We are here tonight to present our proposal for improving
our buildings. You will soon hear from Barbara Kernochan, chair of our building
committee, and Ralph Mechur, our architect, about details of the plan. Members
and friends of our church are also hoping to speak at the appropriate time.
My role is to introduce you to the history and mission of our faith community.
Our Santa Monica church was founded over 75 years ago, when a small group
of Unitarians began meeting in each other’s living rooms. With help
from our Association headquarters in Boston, a minister arrived along with
the funding to build a modest church. Our original building at 18th and Arizona,
a mission-style sanctuary, was designed by the Santa Monica architect John
Byers. The sanctuary remains part of our worship space.
Our Unitarian Universalist faith embraces democratic process and respect
for the inherent worth and dignity of every person. We are an intentionally
inclusive and pluralistic community. Our doors are open to all who wish to
join us regardless of religious background, race, color, sex, sexual orientation,
gender identity, or national origin. Our lively congregation now numbers about
450 adults and 120 children.
When you enter the front doors of our church, you see the words of our covenant,
an historic statement from our faith tradition: “Love is the doctrine
of this church. The quest for truth is its sacrament, and service is its prayer.
To dwell together in peace; to seek knowledge in freedom; to serve humankind
in fellowship; thus do we covenant with each other.”
Over the years, our covenant has guided us in building a community that puts
our faith into action. We are especially proud of our history of community
outreach and involvement. Here are some highlights:
-- Our minister emeritus, the Rev. Ernie Pipes and Rabbi Ernest Block formed
a clergy association that later became the Westside Interfaith Council (1955-1960).
-- The congregation collaborated with the Santa Monica AME Church to set
up one of the area’s first Head Start programs (1966).
-- Cesar Chavez and the United Farm Workers Board members used our church
as a primary site for negotiations between the UFW and a major grower (1973).
-- The congregation voted to become a Sanctuary Congregation for refugees
from El Salvador, Guatemala, and Nicaragua and a dedicated Peace Site (1986).
-- After decades of advocacy for the civil rights of gay, lesbian, bisexual
and transgender persons, we formalized our status as a Welcoming Congregation
(2003).
Our tradition of community involvement and service continues today with our
Faith in Action program. Our congregation provides hundreds of volunteers
to local social service agencies such as the Westside Food Bank, OPCC, and
Step Up on Second. We belong to the Westside Shelter and Hunger Coalition.
Our Peace Site activities include regular public lectures and forums on current
issues.
In addition to our congregation, our buildings offer a resource for groups
in the local community. Nearly every day of the week we host a twelve-step
meeting, or a music recital, or a spirituality program sponsored by members
of the larger community. Shared space nurtures cooperative relationships and
understanding, which we cherish.
The proposed improvements will provide adequate and accessible space for
our congregation and for the larger community. Our mission of service and
civic involvement will be well served by our building program. Thank you for
your time and consideration of our proposal.
Barbara Kernochan:
I am Barbara Kernochan, chairperson of the Building Committee which has undertaken
the church's current efforts to enhance our facilities. We began this process
several years ago as we looked around and realized our buildings were inadequate,
both to accommodate our Sunday worshipers and to house our religious education
program. We discussed the possibility of moving from our home of 75 years
in order to meet our facility needs. Instead, we decided we wanted to stay
in Santa Monica . Our congregation draws primarily from this community, and
it is here that our history lives. Given the very limited square footage of
our two lots on 17th and 18th Streets, we recognize that we can hope only
to accommodate our current programs and that our membership cannot grow much
beyond its current size. Our goal therefore, is to make optimal use of the
space at our current location, with the following three priorities:
1. We need to improve accessibility, safety, and circulation throughout our
buildings.
2. We want to provide appropriate facilities for religious education.
3. And we want to enhance our meeting space in the sanctuary itself.
*Looking first at accessibility and safety issues:
Our buildings are quite old, with numerous obvious shortcomings. There is
no elevator to the classrooms now on the second floor of our 18th Street main
building. Circulation, especially in the upstairs rooms, is downright dangerous
with our current floorplan. Only one bathroom is wheelchair accessible in
the whole complex, and there is no access to the chancel for those who use
a wheelchair or walker.
We would like to provide accessible bathrooms, an elevator and two lifts
in order to address these shortcomings. We plan to replace a rarely used second
stairway on the southside of the fellowship hall with a new stairway on the
northside. Circulation as well as entry and exiting will be improved, with
new doorways opening to gardens and patio areas and better circulation within
the sanctuary itself.
With our religious education program housed in a new 17th Street building,
we can provide elevator access to all our classrooms. Appropriate space for
our religious education program is our second goal. The rooms we currently
use for classrooms and meetings are very small, mostly on the second floor,
and have only marginal access to the outdoors. What we call our nursery is
makeshift in the extreme. On Sunday mornings, we gate off a portion of our
administrative office to care for our infants and toddlers. Instead of sinks
and changing facilities, our little ones share space with file cabinets and
other office furnishings.
We would like to replace our old, cramped classrooms with larger, light-filled
rooms. We want our children to have direct access to secure outdoor spaces.
And we want better meeting spaces for the adult workshops, committees, andother
groups that use these spaces at other times. We desperately need a dedicated
nursery space, with appropriate facilites, sinks and counters, and its own
yard.
*Finally, we look to our sanctuary. With modest growth over the years, we
find ourselves very crowded at Sunday services. Even after moving to two morning
services, we still must provide overflow seating in the fellowship hall, where
the service can be heard, at least, over the public address system.
We hope to widen the sanctuary to better accommodate our Sunday morning congregants.
This will be accomplished not by increasing the building footprint, but by
rearranging the interor space in a manner consistent with solving our access
and circulation problems. A larger chancel allows us to place our piano and
organ in a better location and to provide chancel access via a lift on one
side.
As you review our application, please consider the following points:
1. Our building proposal is designed to address our current needs, not to
provide for future growth by increasing our facility usage or programs. We
want to replace our current classrooms, room for room, and incorporate a modest
additional space into our sanctuary. We do not anticipate that the Westside
will be overrun by Unitarians.
2. In accordance with the principles of our faith,our congregation participates
in a wide range of activities promoting peace, social justice and environmental
causes. Collaborating with numerous community agencies, we are anxious to
continue our work here.
3. We know that Sunday morning services impact neighborhood parking. We provide
off-street parking at this time of high facility usge in order to minimize
this impact, and will continue to do so for the benefit of our neighbors as
well as our members.
4. We have always endeavored to be a good neighbor. At our preliminary meeting
with city planning staff, we were informed that there was not a single complaint
on record regarding our building or usage. Should there be concerns now, we
are ready to work with city staff to find solutions. Thank you for your careful
attention.
February, 2004
Building Additions, Improvements Estimated at $1.8 Million
The congregation met on Sunday, January 25, to review plans and status of
the building program. The good news is much progress has been made toward realizing
a better and more usable facility for the congregation. Everyone who spoke also
emphasized there is still much work to be done. The Rev. Judith Meyer said that
the Building Committee has done tremendous work toward making additions and
improvements a reality.
Carol Kerr, board president, opened the meeting citing three truths: first,
the congregation still must approve final plans, budget and process before construction
can begin; second, design and costs will change, based on changes requested
by the city and by cost considerations identified by the contractor; and third,
the true cost of the building program will not be known until the last invoice
is paid, because this is just the nature of construction projects. Current project
estimate is $1.8 million.
Barbara Kernochan, Building Committee Chair, described the process as a small
building project with the complications of a large project, mostly the result
of its urban setting. She said that Wednesday, March 3 is the tentative date
for presenting the project to the Planning Commission and hopes that the congregation
and neighbors will come out then to support the project. Barbara said the church
has received a very supportive letter from UCLA Santa Monica Hospital. She anticipates
a second Planning Commission appearance before the plan can be approved.
Barbara said there is much planning still to do, including determining whether
to overlap construction of the 17th Street building with additions and changes
to the church and Forbes Hall, which may shorten construction time but would
impose other logistics issues.
Architect Ralph Mechur presented plans and drawings describing the interaction
that must take place with the city and then with the contractor before construction
can begin. If every step goes perfectly, construction might start this summer
and would take between 10 and 14 months to complete.
—Nels Hanson
January, 2004
Next Stop for Our Building is the City of Santa Monica
Many of you may have seen recent articles in the local Santa Monica papers
about complaints from local businesses about the slowness of the Santa Monica
planning department. Well, that’s what we are waiting for and waiting
and waiting.
But we are making progress and have been told by the planners that we will “probably”
get to the planning commission the end of January. The architectural review
board will follow.
The planning department continues to find issues we must address as we go
along, the latest being some changes they want in order to preserve the “historic”
south façade facing 18th Street. We are continuing to work with the contractor
to refine the cost estimates, which is hard to do at such an early stage of
development of the drawings. But soon we hope to be able to report back to the
congregation some more updated cost information. Ultimately, we will not know
the exact cost until the final bids are in after completion of the working drawings,
which will begin after the project is approved by the planning commission.
We are also starting to plan our presentation to the planning commission.
We will let everyone know when that will take place, as we will need to have
a good turnout of supporters. Come to the January 25 Town
Hall meeting for a complete update.
— Barbara Kernochan
November, 2003
Santa Monica Planning Commission is Working on Our Building Proposal
There is still no date on our signboards, but city planner Laura Beck has deemed
our application for a conditional use permit and parking variance complete.
She tells us to expect our hearing before the Planning Commission by early February.
Questions remain, of course. One example: our 18th Street property appears
must be reviewed and approved by the city’s historic consultant. We are
meanwhile considering various landscape and hardscape ideas, with the guidance
of Fran Hotchkiss.
We remain very pleased with the work of our architect, Ralph Mechur. He is
conversant with the sometimes arcane workings of the city approval process and
is a familiar face to many at the city offices. He continues to give generously
of his time, meeting with the Building Committee and various subsets as needed.
The recent bequest to the church comes at a most opportune time. Although
one million dollars has been pledged by our members toward the building program,
this princely sum would suffice to build only one building, not both. Thanks
to the extraordinary generosity of Earl Morgan, completion of the full building
program is once again a realizable goal. With a still considerable gap of about
$300,000 remaining, we must continue working to bring in additional contributions
and perhaps finance a small amount.
The congregation has taken on an ambitious program of facility enlargement
and improvement in order to keep our church
home healthy and strong. As prospects for city action and full funding approach,
our work is becoming more exciting by the day.
-- Barbara Kernochan, for the Building Committee
September, 2003
We Get the City’s First Green Light to Start Our Building/Remodeling
Have you noticed the large signboards in front of the sanctuary and facing
17th Street? They represent a giant step forward in our building process. We
have officially submitted our building proposal to the Santa Monica city planners,
applying for a conditional use permit and parking variance, and those signs
indicate that the city process has begun.
As is customary, alas, our application was deemed incomplete. The city has
posed additional questions about very specific architectural details and even
the types of trees we anticipate planting, and our architect and others have
been busy responding to those remaining queries.
Once our revised application has been deemed complete, the city will give
us a date for our hearing. You will know this step has been taken when a date
appears on those big signs.
Meanwhile, we have requested an itemized breakdown of costs from our selected
construction company.
Our next decision points will focus as much on our financial picture and the
will of the congregation as on the city’s approval process. Stay tuned.
— Barbara Kernochan for the Building Committee
July, 2003
Suppose We Gave a Party...and Nobody Came?
The building process has reached the point where we have invited the neighbors
in to explain our plans and to deal with any objections. We mailed out more
than 300 invitations to the surrounding neighbors and invited them to the church
Sunday afternoon, June 8, for a presentation and Q&A session. We displayed
drawings, illustrations and models of the new building. We prepared refreshments.
The architect and the building committee were present, ready and eager to resond
to any questions or objections.
No neighbors showe up: zero, nil, nada, zilch.
Paradoxically, we are satisfied with the results: it means that the project
is progressing. It means that currently there is no active opposition. It means
that we can demonstrate that to the city. It means we got to eat all of the
brownies.
-- Len Adler, for the Building Committee
June, 2003
Plans, City Approval, and Costs are on Building Committee Agenda
May was a slow month for the building committee. We met only once, while our
architect, Ralph Mechur, reworked his drawings to incorporate the congregation’s
preferences elicited at the March 23 meeting, and our attorney worked to complete
the “findings” to submit to the city. Ralph is also waiting for
appointments with the city planners. This month we will have a reception to
introduce the project to our nearby neighbors.
Our new design utilizes the existing building at the back of our 17th Street
property, adding a new classroom/meeting room building, a bridge connection
to the renovated existing building, an elevator, and bathrooms. The plan leaves
considerable outdoor space along the south side of the new building and in a
plaza between the buildings. The sanctuary plans remain essentially the same,
widening the sanctuary into existing office space, with offices moving upstairs.
We want to reconfigure the Forbes Hall building somewhat, shifting one staircase
to the north end and opening part of the south end for storage. The new plan
meets our congregation-identified need for a large gathering space (the expanded
sanctuary), accessibility in both buildings, a dedicated nursery, and larger,
more flexible classroom and meeting spaces. The congregation’s response
to this new design direction has been very positive.
Financially, the project remains uncertain. As we work closely with an estimator
and/or contractor in the coming months, we will explore ways to address the
need for funding additional to the one million pledged thus far if we wish to
complete the entire building program. Steering the project through the city
process and informing the congregation’s financial decisions will be the
focus of the coming year’s work.
--Barbara Kernochan
May, 2003
Architect Answers Congregation's Questions
A congregational gathering held March 23, after the second service, reinforced
both the need for building enhancements and the support of the congregation
for the design direction we are pursuing. The opening salvos of the war in Iraq
underscored for many of us the importance of a physical space to serve our membership
and the larger community through outreach, essential dialogues, and the worship
that takes place in our church home. Our building program will contribute to
a brighter future for liberal religious thought and activity on the West Side.
We have been listening to the ideas and advice of many individuals, including
Jay Gobus, Kris Langabeer, Kathy Cook, Julie Hill, Warren Mathews, and Fran
Hotchkiss in order to help our new architect design to our needs. We have also
gathered recommendations from subcommittees and task forces on kitchen facilities,
possible Forbes Hall improvements, technical subsystems and maybe even a labyrinth
or meditation maze on 17th Street. We've received comments on a possible new
chancel design and choir placement as well. Thanks to all who are helping move
our design process forward and to those who offered their comments at Sunday's
meeting.
Our architect, Ralph Mechur, walked us through his design, including a refinement
of his original concept for 17th Street and some changes to the main building.
New costs could be added for some very desirable improvements to Forbes Hall
that were not included in his first conceptual design. We are awaiting solid
line-item cost estimates for this new design work. Meanwhile, we are at the
point of submitting our application package to the city planning office. Our
proposal will include our full wish list as shown on current plans, even though
we are uncertain whether we can achieve all of our goals with our current financial
picture. The city process is a lengthy one, but we hope to return to the congregation
in the coming months for a vote on our next steps.
Ralph elaborated on his latest design work. His most recent schematic drawings,
as well as his biographical information, are on display on the kiosk in Forbes
Hall. We hope everyone will take a look at these recent developments. The building
committee stands committed to this project under the wise guidance of our architect,
and wants to express thanks to all who helped us with their questions and comments.
Excitement is, indeed, building.
-- Barbara Kernochan
for the Building Committee
April, 2003
Architect Busy Preparing Drawings
This past month, the building committee has been meeting almost every week
to review the plans being drafted by architect Ralph Mechur. Here are some of
the plas that were presented to the congregation:
After a trial run of placing the choir on the level of the floor, the congregation
was surveyed for feedback on the sound and aesthetics of the location. The vast
majority of respondents found the music to be somewhat better or no different.
Only a few thought it was negatively impacted. The replies on the aesthetics
were hard to judge because at the last minute the piano had to be moved in front
of the choir so the pianist could see the choir director. (The results of the
survey are posted on the building kiosk in Forbes Hall.) The new plans have
the choir director standing on the chancel while the choir seats are at floor
level.
At the back of the chancel is a small room that will house the controls for
the microphones and other sound equipment. The organ and piano will be on the
chancel, off to one side. The current configuration has a mix of pews and chairs,
with the sanctuary seating 213.
The big change in the Forbes Hall building is the moving of the stairway from
the front to the back. This will comply with fire codes, and give us additional
storage areas upstairs and downstairs. The administrative offices will be on
the second floor.
The existing building across the alley will be connected to the new buidling.
The area between has been designed with a dramatic stairway encircling an outdoor
patio. The solid back of the stairway created a dark area in the hallways below
and behind it, so the back was changed to a lattice design. The stairway takes
up a lot of room, but the fire code does not allow it to be placed in a less
conspicuous location. The possibility of creating a permanent laybrinth in the
area between the buildings is being studied. The 17th Street property will have
seven classrooms in the two buildings, plus a spacious nursery. There is also
a space for a teachers' room.
While Ralph is working on the plans to present to the city, Barbara Kernochan
is revising Judith Meyer's "case statement" to reflect these new plans.
This describes who we are: our mission, history in the community, a description
of the project, and our reasons for undertaking it.
About a month ago, Ralph met with the city and was told our parking requirement
is spaces for six cars. This is based on our increased needs due to the added
sanctuary space. The parking does not have to be on site, so the committee is
exploring nearby neighborhood locations we might be able to use.
March, 2003
Town Hall Meeting Planned
On Sunday, March 23, after the second service, there will be a presentation
of the work done to date by our architect, Ralph Mechur. From
the time he took over the project until the end of January, all his attention
was focused on the 17th Street property and working with the city. In February,
he turned his attention to the sanctuary building and Forbes Hall. At our March
town hall meeting, Ralph will present his ideas to the congregation and members
will have an opportunity to ask questions and make suggestions.
In addition to Ralph's plans, there are also some very preliminary plans drawn
by our member, Fran Hotchkiss, who is a landscape designer.
The focus of the design is the courtyard between the existing building on 17th
Street and the new building. After the presentation to the congregation, we
will consider plans for making a presentation to our neighbors.
Finances are an important element in the building equation. The capital campaign
we had last year went pretty well and we appreciate so many members and friends
supporting the program. We do still have additional funds to raise if we are
to successfully complete the full scope of the building program. On March 23,
Jim Cadwell, the chair of the capital campaign committee, will
give a brief update of the status of the campaign.
January, 2003
Update
Following a holiday hiatus, the building committee met on January 5. Some members
had walked an area covering the few blocks surrounding the churcha nd found
about a dozen parking lots that might serve as alternative or backup to the
hospital garage. The owners will be contacted.
Our topographic survey has been completed, identifying setback lines, existing
trees slopes, and other features. The architect has been developing the open
area, or plaza, between the buildings on 17th Street as the focal point and
main design opportunity for the property.
With design progressing well, albeit the city progressing slowly, we look forward
to a presentation in the congregation on March 23, followed by an event for
the neighbors.
-- Barbara Kernochan
December, 2002
Parking and Building Code Requirements
The building committee reports it is pleased with the progress of our architect,
Ralph Mechur, and has signed a "Phase 1" letter contract for the conceptual,
schematic, and detail design necessary to obtain acceptance by the Santa Monica
planning commission, architectural review board and building department. Critical
issues are parking and building code requirements. This phase represents about
15% of the architectural work. Our timing in this phase is determined largely
by the city.
A definite contract for the remainder of the architect's work is being negotiated.
A preliminary services agreement with a building contractor (Dreyfuss) is also
being negotiated.
Three proposals for a topographic survey of the 17th Street property have been
received. The committee has selected the low bidder, subject to the architect's
comments.
Sufficient and assured Sunday parking continues to be a concern. The committee
will investigate the possibility of obtaining offsite parking near 18th and
Arizona. Suggestions from the congregation are welcome.
November, 2002
Pre-Application Review
On September 26, members of the church's building committee met with representatives
of various Santa Monica city departments for a pre-aplication review meeting.
Each city staff member reviewed the potential issues from their department's
point of view. It is still too early in the process to evaluate the city's potential
response to our proposed project, but there were some hopeful signs.
The big issue is, of course, parking. One hopeful sign is their indication
that no new parking spaces would be required for the new classrooms since we
are building the same number of classrooms we have now, even though they are
larger. So their initial take on this is that parking will be required only
for the increase in office space and the increase in the number of seats in
the sanctuary. They have asked for additional documentation on the exact increase
we anticipate. The committee, with the architect, will be working on this information.
The other good news is that the city staff feels we will not be required to
prepare an Enviornmental Impact Report, which would have been time-consuming
and expensive. The other items discussed with the city were about various building
code and fire department issues, all of which can probably be solved.
There was a brief discussion about the Religious Land Use and Institutionalized
Persons Act (RLUIPA) laws and the possible effect on our project. The RLUIPA
passed by Congress in 2000 benefits churches in their rights to expand facilities
regarding local zoning restrictions. We have received nothing definitive from
the city but have gotten some indication that this law may be beneficial in
our case, and that it could help us obtain some concessions on the parking demand.
The committee is working with the architect to resolve his contract to complete
the design phase through approval by the city. The architect, Ralph Mechur,
was once a member of the Santa Monica planning commission and has been very
helpful in maneuvering through City Hall. The attorney, Chris Harding, is well
known in the development community of Santa Monica, and has been very generous
with his time in advising the building committee and attending the meeting with
the city. It will still be many months before getting to the planning commission,
and knowing just how much or what we will be able to build, but everyone remains
hopeful and enthusiastic.
-- David Denton
August, 2002
Cost-Saving Changes
In our capital campaign, we raised a lot of money, and interest in our building
program continues to run high. At our June 30 congregational meeting, the focus
of discussion was seeking ways to live within our means while holding true to
our aspirations. To realize both of these goals, we found, will require a new
architectural direction and a continuing hard look at our bottom line.
Construction estimates for the building design we have been considering these
past months came in at or near $1.5 million, as anticipated. Adding permit costs,
professional fees, insurance, contingency and other indirect costs, we would
need close to $2 million to fund the project. Having raised under $1.1 million
and recognizing the imprudence of taking on a large debt burden, we had to acknowledge
that this scope of work is simply beyond our means.
As a result, the building committee began to look for ways to significantly
reduce the program costs. We looked at several possibilities, from selling the
existing 17th Street building on the alley in order to rebuild Forbes Hall,
to scaling back plans on both properties. We decided that our most promising
path was to devise a more affordable design concept for 17th Street, perhaps
using the existing building on the alley.
We began working with a new architect, Ralph Mechur, who came to us with extensive
experience with non-profit organizations, as well as eight years of service
on the Santa Monica Planning Commission. He rose to the challenge and designed
a plan that brings savings in construction costs and additional reductions in
some soft costs. Approximate costs for the new design, including sanctuary expansion,
are $1,450,000.
This new plan does not give us quite the cost reduction we had looked for,
but it puts us in the ballpark of what we might afford. If we cannot borrow
or raise the shortfall, we might still have to build in phases. Nevertheless,
there is real confidence that our new plan is the right direction for us. Judging
by the reaction of participants in our meeting, the congregation is pleased
with Mr. Mechur's response to his challenge. (Early drawings are posted on the
Forbes Hall kiosk.)
Much remains to be done. With our new plan under development, the building
committee is turning its attention to parking and city requirements. A business
meeting, perhaps in late fall, will allow the congregation to decide our course.
How grand it would be to break ground next summer!
May, 2002
Pledge Milestone!
We're now
celebrating the $1 million mark in pledges for our building and capital
campaign! Thanks to all who helped us get to this point...and if you haven't
pledged yet, it's not too late. Ofelia Lachtman and Carol Kerr will be in Anderson
Courtyard after every service in May to discuss with you how best to contribute
to the capital campaign.
April, 2002
Congregation Discusses Choir Location;
New Building Brochure Available
In a town hall meeting on Sunday, March 17, the congregation met in
response to a request from many members who suggested that the choir in the
new sanctuary not be placed behind the minister and in front of the greenery.
The meeting was led by President Jerry Gates and Building Committee
Chair Barbara Kernochan. Architect Aleks Istanbullu was there
to hear the congregation's concerns and to answer questions regarding the current
configuration. Steve Wight explained that the choir has to be near the
piano, so the choir director can be seen by the singers and the pianist, and
that they must face into the audience.
Most people thought the choir in the back was not a solution. A number of considerations
regarding the placement of the choir were fully discussed, including a location
on the side rather than along the back behind the minister, having the choir
turn to face the congregation when they sing, or move a few feet from their
seats to stand facing the congregation. Another idea was to have the choir on
the left next to the green area instead of in front of it. Most people thought
it was more important to have a deep green area than to have it shallow and
along the entire chancel. The current plans show the green area as narrowed
and twice its current length.
This process was said to have been worth while, and the hope was expressed
that future major decisions about the building will be brought to the congregation.
President Jerry Gates agreed, and urged people to be active participants in
the process. He summarized the discussion, saying that those present wanted
chancel greenery similar to what we now have, fine acoustics, and flexibility
of use. Further, he said that it was agreed that the design should permit maximum
seating for the congregation. The builsding committee will work with the architect
to meet these desires.
Also in March, we published a new brochure, "Building
on our Future: Capital Campaign 2002," which presents all the details of
our new building and capital campaign. It contains quotes
from church members on what the campaign and the church mean to them, detailed
building plans, and options
for donating to the campaign. You can read
the full text of the brochure here (be sure to zoom in on various sections
after the image appears in your browser window), or obtain a hard copy from
the church office.
March, 2002
Design Suggestions from the Congregation
Following presentations to the congregation earlier this year, the Building
Committee received valuable suggestions from members of the congregation. All
questions and suggestions have been reviewed by the committee and brought to
the architect as well. Although not all suggestions are feasible, because of
city codes, costs, or other considerations, it is wonderful that the congregation
is taking such an active role in the building program. Here below are the suggestions,
followed by a feasibility assessment of each:
Use the storage space adjacent to left side of chancel as a bathroom.
Although this space is already plumbed, we are concerned that a bathroom directly
adjacent to the chancel would pose potential noise problems. We do provide the
two bathrooms just inside the Arizona entrance. Perhaps most importantly, this
chancel-adjacent location is critically needed for the audio and electrical
equipment and wiring, and for storage.
A short wall or partial glass wall would create a more welcoming administration
office upstairs.
This will costs a little more, but can be done and would create an attractive
entry. Marie will be asked to assist in the layout of this area.
Keep foyer bathrooms on the east wall at the sanctuary entrance, as far
removed from sanctuary seating as possible.
Doors would have to open towards the sanctuary to afford wheelchair access.
As drawn, there is a thick wall between sanctuary and bathrooms, and sound-proofing
can be added. Doors (with glass panels) could replace the curtains, further
insulating the sanctuary from foyer noise.
Is there enough storage space? A basement in the West Building would provide
additional storage space.
A task force is analyzing our storage needs now, and we know that inexpensive
off-site storage is available for items used only infrequently. However, a basement
or partial basement would be great if we can afford it. We would have to add
an elevator stop, thus necessitating a more expensive three-stop elevator, and
of course excavate and ventilate. As we look at possible construction companies,
we are asking specifically for a cost estimate on a basement. With numbers in
hand we can decide if the additional storage is worth the additional cost.
Remove the bit of wall that descends from the roof to separate the central
area from the north seating area of the sanctuary.
This is a structural requirement to support the central clerestory. It will
be repeated on the south side when the wall is removed.
Video wiring would allow for remote viewing in the foyer and/or Forbes Hall.
Yes, we would like to provide some remote viewing options for services and
other events, so this would be a practical and welcome addition. We have not
yet reached the stage of mechanical details, but we need to find out what is
in place now and make sure that additional wiring is included during renovation.
Then the cameras and monitors can be added as funds become available.
Let's reconsider a ramp up to the chancel.
We are required to provide wheelchair access to the chancel. Our initial architectural
drawings tried several possible ramp configurations, but a ramp uses up a great
deal of space, no matter how it is placed. Although a lift can look awkward,
we can work to make the lift look more attractive rather than sacrificing floor
space. To increase seating space in the sanctuary has always been a primary
considerations for the whole building program and we are working hard to maximize
that space.
Reconfigure the Forbes Hall hallway into table and chair storage to streamline
Forbes Hall.
There are certain code restrictions regarding lengths of dead-end hallways,
but this idea is a real possibility and may indeed be a better use for this
little-used space. However, certain built-in areas on the south wall of Forbes
Hall must remain, as they contain a video monitor, wiring, the new phone system,
and storage areas. Further study is needed here.
Relocate the choir, preferably to the back of the sanctuary.
Our first sanctuary task force suggested this placement, but when presented
in the early architectural drawings, many people objected. The primary consideration
is space. To make room for the choir, conductor, piano and organ in the back,
rows of seating would have to be removed. In order to retrieve that seating
space, we would need to shrink the chancel, making it far less desirable for
weddings, concerts, and other events. All input from the music program indicated
that the piano should be on the chancel, that the piano and organ must be on
the same side, and that for reasons of acoustics the choir should face towards
the congregation. Furthermore, by utilizing the recessed area, we actually gain
chancel space without sacrificing sanctuary seating. In the current design,
the choir sits behind and to the left of the minister and, of course, will be
seated except when performing.
Reserve the library in the West Building as sacred space.
While there will be no sinks, and surfaces will be more formally finished than
in the other classrooms, the library may sometimes be needed as a classroom
for our young people. It will not be used in ways that could easily mar or stain
walls and flooring.
There could be a lot of disturbance from street activity and noise through
the French doors to the Memory Garden.
Bamboo or other greenery will help screen street activity. The glass will be
dual glazed for maximum sound insulation, and the doors will usually remain
closed during services.
We want to keep the plantings behind the chancel.
That wall of green is very popular. It will remain, but in a different form.
With the choir seated in front of the lower portions, the planting area will
not be as deep as it is now. However, it will extend all the way to the current
south wall, thus almost doubling in length. Also, the memory garden greenery
will be visible through the new doors on the south side of the sanctuary.
Why isn't the West Building designed in Mission Style?
While we all love the styling of the sanctuary, the new West Building is not
adjacent to it, but rather to Forbes Hall. Although less traditional than mission
style, a clean-lined modern building can be equally beautiful and uplifting.
It is clear that we do not all have the same architectural or aesthetic sense,
since we are hearing a lot of differing ideas on design details. But there is
broad consensus that the design must serve to unify the campus. The architect
and Building Committee are exploring a number of ways to accomplish this, such
as recreating some sanctuary design elements in the new building, selecting
coordinating colors and materials, and/or creating a stepping-stone pathway
linking the buildings. We continue to welcome your ideas.
December, 2001
Plans Revealed; Vote Scheduled for Dec. 9
The preliminary building plans shown to the congregation on November 4 describe
a remodeled sanctuary, and administrative offices for the second floor, above
Forbes Hall.
The new building has six classrooms, which can also serve as meeting rooms.
There will be a library or multi-purpose room on the second floor, accessible
by stairs and elevator. There will be outdoor play areas for the children.
The sanctury will be expanded by removing the wall between it and the existing
offices. The piano and organ will be on the same side, so the organist will
no longer have to cross in front of the chancel. The choir will sit along the
back of the chancel. French doors along Arizona Avenue will let in the light
and provide access to a memory garden. There will also be a second restroom
in the south annex.
Instead of an elevator, Forbes Hall will have a lift allowing access to the
second floor, and to the sanctuary. The second floor above Forbes Hall will
include offices for the minister, the director of religious education, the church
administrator and administrative assistants. There will also be a room for volunteers
and one room to serve as a choir room, music director's office and musicians'
green room.
We will have four parking spaces on the alley side of the 17th Street property,
replacing the garages that are there now, but never used for cars.
During the meeting, members of the congregation gave their feedback on the
plans. The building committee will review all suggestions and take them back
to the architect. A final decision on whether to go ahead with the building
and the capital campaign will be made at the congregational meeting at 12:30
on Sunday, December 9.
November, 2001
Everyone Invited to Unveiling of Latest Building Plans
On Sunday, November 4, at 12:30 p.m. in the Sanctuary, members
of our church's building committee will present the latest renderings of the
architectural plans for our new building program.
These latest and more detailed plans are the culmination of several years of
gathering member input on what we want for our church. The building project
had its genesis in the "visioning" process. Small neighborhood meetings were
held about four years ago. Members discussed their wishes for the church and
the dominant theme was the need for more space.
A subsequent meeting has been referred to as "the one with dots." Members brainstormed
ideas for what we all wanted to build. After lengthy discussions, we voted by
placing sticky dots on large sheets of newsprint listing the ideas. The runaway
winners were an enlarged sanctuary and enhanced classroom space.
A facility development committee was formed to further explore the ideas from
the congregation. They presented the ideas to an architect, Aleks Istanbullu,
who developed three rough plans, based on different levels of funding. On February
29, 2000, about 75 members met all afternoon with the architect to tell him
what we wanted. He presented the design concepts to the entire group, and then
small groups met at tables set up in Forbes Hall to look at the plans and discuss
the concepts.
Each group reported back, and the consensus was remarkable. The conclusion
was that the most important improvements were an expanded sanctuary, a new classroom
building, and administrative offices were the classrooms now are. We did not
want our social hall relocated across the alley. Armed with those ideas, the
architect proceeded. He met with many groups from the congregation, focusing
on people whose volunteer or staff activities would be most affected by the
project. At a January 28, 2001 meeting, the congregation voted to proceed with
the capital fundraising campaign.
This March, a building project committee was formed, and in June, the committee
published a comprehensive update on the status of the planning. To summarize:
the city planning department had been encouraging; we are unlikely to be able
to build all that we would like to, but we may be able to do the most important
parts; the architect was about to start on the schematic drawings, better defining
the scope of the project.
Our November presentation will be an important step as we prepare to go into
the final stages of our planning process. This is your opportunity to see where
we are, ask questions, get clarifications, let your thoughts be known, and in
general get excited about our building prospects. Copies of the latest design
will be distributed. The building committee will gather any additional input
and pass it on to the architect for review. We encourage members, friends and
visitors to attend this meeting. A light snack, for a modest charge, will be
available after the 11 a.m. service.
June, 2001
Capital Campaign Plans Coming Together
At the June meeting of the church board, capital campaign chair Jim Cadwell
reported that the architect for the building program has been instructed to
draft a revised budget for preparing the building plans. Also, 54 people attended
two capital campaign orientation meetings held in May by UUA consultant Jerry
King. November 4 is our scheduled kickoff date for the capital campaign.
The Steering Committee met on June 19 to start filling key management positions
in the campaign. Pledge campaign co-chair Anita Brenner attended the
meeting to help coordinate the Pledge and Capital campaigns. Also, a telephone
conference was held on June 14 with Jerry King to discuss a start date for solicitations.
May, 2001
Current Project Plans and Revisions
Barbara Kernochan reported progress in discussions with Santa Monica city officials
about various approvals needed for our church's proposed building program. She
noted that plans for a bridge across the alley connecting the second floor of
Forbes Hall to a new religious education building on 17th Street have been shelved
because a bridge would have to be higher than the roof of Forbes Hall so trucks
could pass.
Plans now call for a two-story structure on 17th Street for religious education
classes, meeting rooms, and other uses, for enlarging the sanctuary by extending
it south into the current office space, and for the renovation of upstairs rooms
into office space.
Jim Cadwell reported that the project cost and capital campaign goal has been
revised to $1.5 million. Capital Campaign organizers held orientation meetings
on May 22 and 23 for small groups of members, as the beginning of involving
everyone in the campaign efforts.
Annual Report to the Congregation
On Sunday, May 20, Barbara Kernochan reported:
1. We have met with the Santa Monica Planning Department. Senior planning staff
were encouraging about our building proposal, noting that two church expansion
projects similar to ours met with approval this past year. We now know exactly
what documents will need to be submitted in our own approval process. Our land-use
attorney will file Parking Variance and Conditional Use Permit applications
on our behalf. We have also learned that the city is willing to extend our finish
deadline to ten years, which allows us enormous flexibility. We are in the process
of updating our facility usage survey and have sent a letter of intent to Santa
Monica-UCLA Medical Center to open negotiations for a parking agreement.
2. Financials: We have set our capital campaign goal. The figure will not allow
us to build all that we would like, but it is an attainable goal, given the
size of our congregation and the history of generosity we have established.
We may indeed look to creative financing in order to make up some shortfall,
as many congregations must do. The establishment of a clear fundraising goal
is an important step in clarifying the building program, and has brought our
architect's challenge into sharp focus.
3. Architecture: The board has instructed that our architect proceed to the
schematic drawing phase, thus defining the scope of work every more clearly.
The elements we are requesting remain as before: a new building on 17th Street,
with nursery, classroom/meeting rooms, and library/multi-use space, a 30% increase
to our sanctuary space, a reconfiguration of the upstairs into administrative
offices, accessibility including two elevators and redesigned circulation, exterior
elements to include some parking, play space and memory garden. Overall, a place
of good bones, light, movement, and beauty. We are no longer looking for a bridging
of the alley, nor any major renovation to Forbes Hall. A structural engineer
has assessed Forbes Hall and recommends we leave it intact. As the schematic
work reaches completion, the current cost uncertainties will be minimized, and
we can cost out the project with some degree of accuracy. We look forward to
architectural drawings in the next few months, to finally give substance to
our long-held vision.
April, 2001
Updates
At the April board meeting, Pat Barnicoat, a loan officer at First Federal
Bank, explained the criteria for a church receiving building loans from a bank...and
recommended we "raise a lot of money." Rod Lane presented the building
update, including news that connecting the proposed bridge over the alley to
Forbes Hall will be very costly, because the building has many peculiarities
and infirmities. Tearing down Forbes Hall, however, would require changes in
our setback, parking and other requirements. A less expensive alternative to
the bridge would be a crosswalk with a crossing guard.
March, 2001
Building Committee Forms
Thanks to overwhelming congregational approval to proceed with a building program,
a Building Committee is now taking form to guide and oversee the facility improvements
and construction we hope to undertake. Several church members have already stepped
forward to offer insights and expertise in useful areas, from construction to
creative project development to clarifying the sometimes convoluted workings
of city planning. Members of the new Building Committee are: Abby Arnold,
Wally Boag, David Denton, Jay Gobus, Mel Horan, Rod Lane, Kevin Pierik, Judy
Schonebaum and Greg Wood. Barbara Kernochan chairs the group.
Pat Mcguire has been asked to evaluate our potential to relocate to another
westside site, as a key alternative to the building plan. Church members wishing
to offer their talents to the building program may contact Barbara via e-mail
or phone.
February, 2001
Healthy Discussion at January 28 Congressional Meeting
At our congregational meeting on January 28, church members engaged in a vigorous,
healthy dialogue about our building and cap |